[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107160":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107160,782,2,"多选题","发包人进度计划编制注意事项中，（ ）里程碑节点确定时，应考虑分标方案。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工准备",true,{"key":16,"text":17,"correct":14},"B","主体工程施工",{"key":19,"text":20,"correct":21},"C","建设工期",false,{"key":23,"text":24,"correct":21},"D","基础工程施工",{"key":26,"text":27,"correct":21},"E","结构工程施工","AB","本题考查的是发包人控制性进度计划的编制。发包人进度计划编制注意事项中，施工准备和主体工程施工里程碑节点确定时，应考虑分标方案",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]