[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107159":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107159,782,2,"多选题","当存在工程未完全完工但部分工程投产的情况时，应注意施工和运行部分工程的交叉问题，避免互相干扰，影响（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工期",true,{"key":16,"text":17,"correct":14},"B","工程施工",{"key":19,"text":20,"correct":21},"C","费用控制",false,{"key":23,"text":24,"correct":21},"D","管理难度",{"key":26,"text":27,"correct":14},"E","运行安全","ABE","本题考查的是发包人控制性进度计划的编制。发包人安排进度计划时，当存在工程未完全完工但部分工程投产的情况时，应注意施工和运行部分工程的交叉问题，避免互相干扰，影响工期、工程施工和运行安全。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]