[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107158":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107158,782,2,"多选题","下列属于RSM法的主要步骤的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","绘制时标网络的每单位时间的资源需要量动态曲线",true,{"key":16,"text":17,"correct":18},"B","最终检查网络计划，确定是否存在资源冲突",false,{"key":20,"text":21,"correct":14},"C","修正调整后的网络计划及资源需要量动态曲线",{"key":23,"text":24,"correct":14},"D","根据式△Tij=EFi-LSj，逐步调整引起冲突的工作，直到冲突得到解决",{"key":26,"text":27,"correct":18},"E","调整过程中如果有工期延长，按照调整资源冲突且延长工期的方案","ACD","本题考查的是网络计划优化。RSM法的主要步骤如下：（1）绘制时标网络的每单位时间的资源需要量动态曲线。（2）由前向后逐时段检查网络计划，确定是否存在资源冲突。（3）根据式△Tij=EFi-LSj，逐步调整引起冲突的工作，直到冲突得到解决。（4）修正调整后的网络计划及资源需要量动态曲线。（5）重复（2）、（3）、（4）步骤，直到每个时段都不存在资源冲突。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]