[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107156":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107156,782,2,"多选题","工作可压缩的时间，可受到（ ）约束限制。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","工作本身的最快历时的限制",true,{"key":16,"text":17,"correct":14},"B","非关键时差的限制",{"key":19,"text":20,"correct":14},"C","平行关键路线的结束限制",{"key":22,"text":23,"correct":14},"D","紧缩的关键路线的结束限制",{"key":25,"text":26,"correct":27},"E","关键时差的限制",false,"ABCD","本题考查的是网络计划优化。得到了一条选择压缩工作对象的规则，但该工作究竟可以压缩多长时间，可能受到以下的约束限制：（1）工作本身的最快历时的限制；（2）非关键时差的限制；（3）平行关键路线的结束限制；（4）紧缩的关键路线的结束限制。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]