[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107155":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107155,782,2,"多选题","将串联工作改为平行交叉工作的特点是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","不改变工序间的逻辑关系",true,{"key":16,"text":17,"correct":14},"B","不缩短各工序总的持续时间",{"key":19,"text":20,"correct":21},"C","不违反工艺要求",false,{"key":23,"text":24,"correct":21},"D","减少资源",{"key":26,"text":27,"correct":21},"E","能收到最大的优化效果","AB","本题考查的是网络计划优化。将串联工作改为平行交叉工作的特点是不改变工序间的逻辑关系，不缩短各工序总的持续时间，只是将串联进行的关键工序各自细分成几段，然后进行平行交叉作业。选项CE属于平行工作特点。选项D，组织平行交叉作业，首先应符合工作之间的逻辑关系，有可能要增加资源。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]