[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107154":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107154,782,2,"多选题","工作历时估估算方法中，在缺少经验数据时，综合调整系数可参考取值正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","当t≤7天时，K=1.25～1.4",true,{"key":16,"text":17,"correct":18},"B","当t≤7天时，K=1～1.4",false,{"key":20,"text":21,"correct":14},"C","当t＞7天时，K=1～1.25",{"key":23,"text":24,"correct":18},"D","当t＞7天时，K=1～1.4",{"key":26,"text":27,"correct":18},"E","当t＞7天时，K=1.25～1.4","AC","本题考查的是网络计划编制。工作历时估估算方法中，在缺少经验数据时，综合调整系数可参考取下列值：当t≤7天时，K=1.25～1.4；当t＞7天时，K=1～1.25。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]