[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107153":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107153,782,2,"多选题","参数估算中，若已有各结构物的设计图纸，应根据设计图纸并考虑（ ）因素计算相应工程量。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","工程分期",true,{"key":16,"text":17,"correct":14},"B","分层",{"key":19,"text":20,"correct":14},"C","分段",{"key":22,"text":23,"correct":24},"D","新技术",false,{"key":26,"text":27,"correct":24},"E","新工艺","ABC","本题考查的是网络计划编制。参数估算中，若已有各结构物的设计图纸，就应根据设计图纸，并考虑工程分期、分层、分段等因素，分别计算出相应的工程量。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]