[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107149":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107149,782,2,"多选题","某工程单代号搭接网络计划如下图所示，节点中下方数字为该工作的持续时间，其中关键工作有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工作A",false,{"key":16,"text":17,"correct":14},"B","工作B",{"key":19,"text":20,"correct":21},"C","工作C",true,{"key":23,"text":24,"correct":14},"D","工作D",{"key":26,"text":27,"correct":21},"E","工作E","CE","本题考查的是搭接网络计划方法。总时差最小的工作为关键工作。从网络的起点到终点均为关键工作，且所有工作的时间间隔均为零的路线为关键路线。考前押题，金考典软件考前更新，下载链接 www.jinkaodian.com 关键线路为C→E→F。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]