[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107148":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107148,782,2,"多选题","某工程双代号时标网络计划如下图所示，由此可得正确的结论有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工作A为关键工作",true,{"key":16,"text":17,"correct":14},"B","工作B的自由时差为2天",{"key":19,"text":20,"correct":21},"C","工作C的总时差为零",false,{"key":23,"text":24,"correct":21},"D","工作D的最迟完成时间为第8天",{"key":26,"text":27,"correct":21},"E","工作E的最早开始时间为第2天","AB","本题考查的是双代号时标网络计划及新横道图。选项C错误，工作C的总时差为2天；选项D错误，工作D的最迟完成时间为第9天；选项E错误，工作E的最早开始时间为第5天。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]