[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107147":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107147,782,2,"多选题","某工程单代号网络计划如下图所示（图中节点上方数字为节点编号），其中关键路线有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","1—2—3—8",false,{"key":16,"text":17,"correct":18},"B","1—2—3—6—8",true,{"key":20,"text":21,"correct":14},"C","1—2—5—6—8",{"key":23,"text":24,"correct":18},"D","1—2—5—7—8",{"key":26,"text":27,"correct":14},"E","1—4—7—8","BD","本题考查的是关键路线法（CPM）。依次计算各选项工期，选项A，不存在；选项B，工期26天；选项C，工期23天；选项D，工期26天；选项E，工期19天，关键线路为B、D。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]