[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107146":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107146,782,2,"多选题","某工程双代号网络计划中各个节点的最早时间和最迟时间如下图所示，图中表明（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工作1—3为关键工作",false,{"key":16,"text":17,"correct":14},"B","工作2—4的总时差为2",{"key":19,"text":20,"correct":21},"C","工作2—5的总时差为1",true,{"key":23,"text":24,"correct":21},"D","工作3—6为关键工作",{"key":26,"text":27,"correct":21},"E","工作5—7的自由时差为4","CDE","本题考查的是关键路线法（CPM）。选项A错误，工作1-3为非关键工作；选项B错误，工作2-4的总时差=9-4-2=3。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]