[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107145":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107145,782,2,"多选题","某工程单代号网络计划如下图所示，其中关键工作有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作A",true,{"key":16,"text":17,"correct":18},"B","工作B",false,{"key":20,"text":21,"correct":14},"C","工作C",{"key":23,"text":24,"correct":18},"D","工作D",{"key":26,"text":27,"correct":14},"E","工作E","ACE","本题考查的是关键路线法（CPM）。关键线路为①→②→④→⑥→⑦→⑩，关键工作为ACEH。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]