[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107144":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107144,782,2,"多选题","下列关于单代号网络图的说法中，叙述正确的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","当网络图中有多项开始工作时，应增设一项虚拟的工作S",true,{"key":16,"text":17,"correct":14},"B","当网络图中有多项结束工作时，应增设一项虚拟的工作F",{"key":19,"text":20,"correct":14},"C","单代号网络图中，有必要时需增加虚拟起点节点和终点节点",{"key":22,"text":23,"correct":24},"D","绘制单代号网络图比绘制双代号网络图困难得多",false,{"key":26,"text":27,"correct":14},"E","单代号网络图中不需要增加虚箭线","ABCE","本题考查的是网络计划技术基本知识。选项D错误，单代号网络图的绘制比双代号网络图的绘制简便，因为它不需要增加虚箭线。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]