[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107143":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107143,782,2,"多选题","某分部工程双代号网络计划如图所示，绘制错误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","有多个起点节点",true,{"key":16,"text":17,"correct":18},"B","有多个终点节点",false,{"key":20,"text":21,"correct":18},"C","工作代号重复",{"key":23,"text":24,"correct":14},"D","节点编号有误",{"key":26,"text":27,"correct":14},"E","有多余虚工作","ADE","本题考查的是网络计划技术基本知识。选项A正确，图中有①和③两个起点节点；选项D正确，③节点指向②节点，是节点编号的错误；选项E正确，⑦→⑧这项虚工作是多余的，工作⑤→⑦和工作④→⑦两项工作直接指向结束节点即可。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]