[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107142":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107142,782,2,"多选题","某工程双代号时标网络计划如下图所示（单位：天），关于时间参数的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作B的总时差为0",true,{"key":16,"text":17,"correct":18},"B","工作E的最早开始时间为4",false,{"key":20,"text":21,"correct":14},"C","工作D的总时差为0",{"key":23,"text":24,"correct":18},"D","工作I的自由时差为1天",{"key":26,"text":27,"correct":14},"E","工作G的总时差为2天","ACE","工作E 最早开始时间为2；工作I 自由时差为0。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]