[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107140":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107140,782,2,"多选题","下列选项，属于监理单位在进度控制中的职责与权利的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","确定建设工期目标",false,{"key":16,"text":17,"correct":18},"B","签发开工通知",true,{"key":20,"text":21,"correct":18},"C","审批承包人提供的施工进度计划",{"key":23,"text":24,"correct":18},"D","按合同规定权限处理施工暂停事宜",{"key":26,"text":27,"correct":18},"E","处理工期延误或提前有关事宜","BCDE","监理单位在进度控制中的职责与权利包括：①签发开工通知；②审批承包人提供的施工进度计划；③监督、检查施工进度，发现进度拖后时指示承包人采取有效措施赶上进度；④按合同规定办理或组织办理向承包人提供施工图纸、提供发包人采购的设备、提供施工道路与场地；⑤按合同规定权限处理施工暂停事宜；⑥主持监理例会，研究、协调、批准、指示、认可有关进度事宜；⑦分析进度状况，对存在的问题提出建议与意见，编写进度报告；⑧组织或参与合同项目完工验收，协商核定实际完工日期；⑨处理工期延误或提前有关事宜。A项是项目法人在进度控制中的职责与权利。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]