[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107138":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107138,782,2,"多选题","公路工程施工监理阶段划分为哪些阶段？（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工前准备",false,{"key":16,"text":17,"correct":18},"B","施工准备",true,{"key":20,"text":21,"correct":18},"C","施工",{"key":23,"text":24,"correct":14},"D","施工验收",{"key":26,"text":27,"correct":18},"E","交工验收与缺陷责任期","BCE","公路工程施工监理阶段划分为施工准备、施工、交工验收与缺陷责任期三个阶段。监理合同签订之日至合同工程开工令确定的开工之日为施工准备阶段；合同工程开工之日至合同工程交工验收申请受理之日为施工阶段；合同工程交工验收申请受理之日至缺陷责任中止证书签发之日为验收与缺陷责任期阶段。公路机电工程监理应增加试运行期阶段。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]