[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107135":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107135,782,2,"多选题","按照项目建设各阶段的特征及其对工期的控制作用，建设工期的阶段包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程准备阶段",true,{"key":16,"text":17,"correct":18},"B","工程施工阶段",false,{"key":20,"text":21,"correct":18},"C","工程评价阶段",{"key":23,"text":24,"correct":14},"D","工程主体阶段",{"key":26,"text":27,"correct":14},"E","工程完建阶段","ADE","一般来说，可按照项目建设各阶段的特征及其对工期的控制作用，将建设工期分为以下几个阶段：①工程准备阶段。工程准备阶段指从临时工程开工起至坝（闸）工程河床基坑开挖或引水式电站主体工程开始施工的时间；②工程主体阶段。工程主体阶段指从河床基坑或引水道、厂房开挖起至枢纽工程开始发挥效益或电站第一台机组开始发电的时间；③工程完建阶段。工程完建阶段指从枢纽工程开始发挥效益或电站第一台机组开始发电起至工程竣工的时间。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]