[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107133":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107133,782,2,"多选题","按照《水利水电工程标准施工招标文件（2009年版）》的规定，合同工期按照如下合同条款确定，下列表述正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合同工期不包括按照合同约定给予的工期变更",false,{"key":16,"text":17,"correct":18},"B","开工通知是指监理人通知承包人开工的函件",true,{"key":20,"text":21,"correct":14},"C","监理人可以直接发出开工通知",{"key":23,"text":24,"correct":18},"D","完工日期是合同工程完工日",{"key":26,"text":27,"correct":18},"E","实际完工日期以合同工程完工证书中写明的日期为准","BDE","本题考查的是建设项目进度控制概述。选项A错误，合同工期指承包人在投标函中承诺的完成合同工程所需的时间，包括按照合同约定给予的工期变更；选项C错误，监理人应在开工日期7天前向承包人发出开工通知。监理人在发出开工通知前应获得发包人的同意",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]