[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107132":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107132,782,2,"多选题","建设项目进度控制基本程序包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","保证进度计划的严肃性与约束力",false,{"key":16,"text":17,"correct":18},"B","进度计划实施中的跟踪检查",true,{"key":20,"text":21,"correct":18},"C","对收集的资料进行整理.统计和分析",{"key":23,"text":24,"correct":18},"D","研究进度纠偏措施",{"key":26,"text":27,"correct":18},"E","进度纠偏措施的实施与监督","BCDE","本题考查的是建设项目进度控制概述。选项A属于进度控制的必要性的内容。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]