[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107131":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107131,782,2,"多选题","编制竣工财务决算应具备的条件包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","经批准的初步设计、项目任务书所确定的内容已完成",true,{"key":16,"text":17,"correct":18},"B","已完成全部工程投资",false,{"key":20,"text":21,"correct":14},"C","建设资金全部到位",{"key":23,"text":24,"correct":14},"D","竣工（完工）结算已完成",{"key":26,"text":27,"correct":14},"E","涉及移民安置的事项已处理完毕","ACDE","编制竣工财务决算应具备下列条件：①经批准的初步设计、项目任务书所确定的内容已完成；②建设资金全部到位；③竣工（完工）结算已完成；④未完工程投资和预留费用不超过规定的比例；⑤涉及法律诉讼、工程质量、移民安置的事项已处理完毕；⑥其他影响竣工财务决算编制的重大问题已解决。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]