[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107129":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107129,782,2,"多选题","评价的内容大体上可以分为全过程评价和阶段性评价或专项评价两类。下列各项中，属于全过程评价内容的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","过程评价",true,{"key":16,"text":17,"correct":18},"B","经济后评价",false,{"key":20,"text":21,"correct":18},"C","生产经营评价",{"key":23,"text":24,"correct":14},"D","水土保持评价",{"key":26,"text":27,"correct":14},"E","社会影响评价","ADE","项目后评价的内容大体上可以分为两种类型。一类是全过程评价，即从项目的立项决策、勘测设计等前期工作开始到项目建成投产运行若干年以后的全过程进行评价，其主要内容包括：①过程评价；②经济评价；③环境影响评价；④水土保持评价；⑤移民安置评价；⑥社会影响评价；⑦目标和可持续性评价。另一类是阶段性评价或专项评价，可分为：①勘测设计和立项决策评价；②施工监理评价；③生产经营评价；④经济后评价；⑤管理后评价；⑥防洪后评价；⑦灌溉后评价；⑧发电后评价；⑨资金筹措使用和还贷情况后评价。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]