[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107127":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107127,782,2,"多选题","工程计量时，监理人应予计量的工程量有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包人超出设计图纸和设计文件要求所增加的工程量",false,{"key":16,"text":17,"correct":18},"B","工程量清单中的工程量",true,{"key":20,"text":21,"correct":14},"C","有缺陷工程的工程量",{"key":23,"text":24,"correct":18},"D","工程变更导致增加的工程量",{"key":26,"text":27,"correct":14},"E","承包人原因导致返工的工程量","BD","对于不符合合同文件要求的工程，承包人超出施工图纸范围因承包人原因造成返工的工程量，不予计量。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]