[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107125":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107125,782,2,"多选题","投资局部偏差的含义包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","单项工程的投资偏差",true,{"key":16,"text":17,"correct":14},"B","单位工程的投资偏差",{"key":19,"text":20,"correct":14},"C","分部分项工程的投资偏差",{"key":22,"text":23,"correct":14},"D","每个控制周期所发生的投资偏差",{"key":25,"text":26,"correct":27},"E","建设项目的投资偏差",false,"ABCD","所谓局部偏差，有两层含义：①对于整个项目而言，指各单项工程、单位工程及分部分项工程的投资偏差；②对于整个项目已经实施的时间而言，是指每个控制周期所发生的投资偏差。累计偏差是一个动态的概念，其数值总是与具体的时间联系在一起，第一个累计偏差在数值上等于局部偏差，最终的累计偏差就是整个项目的投资偏差。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]