[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107124":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107124,782,2,"多选题","根据《水利水电工程标准文件》，承包人提交的完工付款申请单应包括的内容有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","完工结算合同总价",true,{"key":16,"text":17,"correct":14},"B","发包人已支付承包人的工程价款",{"key":19,"text":20,"correct":14},"C","应扣留的质量保证金",{"key":22,"text":23,"correct":24},"D","应返还的履约保证金",false,{"key":26,"text":27,"correct":14},"E","应支付的完工付款金额","ABCE","承包人应在合同工程完工证书颁发后28天内，按专用合同条款约定的份数向监理人提交完工付款申请单，并提供相关证明材料。完工付款申请单应包括：①完工结算合同总价；②发包人已支付承包人的工程价款；③应扣留的质量保证金；④应支付的完工付款金额。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]