[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107117":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107117,782,2,"多选题","下列各项中，包括在预备费中的项目包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","预防自然灾害所采取的措施费用",true,{"key":16,"text":17,"correct":18},"B","地质勘测资料不准，引起地基加固、基础加深所增加的技术处理费用",false,{"key":20,"text":21,"correct":14},"C","市场材料浮动价差",{"key":23,"text":24,"correct":18},"D","国家规定允许调整的材料差价",{"key":26,"text":27,"correct":14},"E","由于图纸的一般错误而产生的经济签证费用","ACE","预备费的适用范围包括：①在进行技术设计、施工图设计和施工过程中，在批准的初步设计范围内的一般设计变更、材料代用等增加的费用；②国家允许调价范围以外的设备、材料价格和工资单价的价差，即所谓市场材料浮动价差；③由于一般自然灾害所造成的少量损失和预防自然灾害所采取的措施费用；④在上级主管部门组织竣工验收时，为鉴定工程质量而必须开挖和修复隐蔽工程的费用；⑤由于图纸的一般错误及现场发生的技术问题处理而产生的经济签证费用。BD两项不包括在预备费中。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]