[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107115":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107115,782,2,"多选题","下列费用中，包含相应项目工程单价或总价中，发包人不另行支付的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","塌方清理",false,{"key":16,"text":17,"correct":18},"B","植被清理",true,{"key":20,"text":21,"correct":18},"C","土方明挖超挖量",{"key":23,"text":24,"correct":18},"D","弃土处理",{"key":26,"text":27,"correct":18},"E","开采区清理、恢复和绿化","BCDE","A项，塌方清理按施工图纸所示开挖轮廓尺寸计算的有效塌方堆方体积以m3为单位计量，由发包人按《工程量清单》相应项目有效工程量的每立方米工程单价支付。B项，承包人完成规定的“植被清理”工作所需的费用，包含在《工程量清单》相应土方明挖项目有效工程量的每立方米工程单价中，发包人不另行支付。C项，施工过程中增加的超挖量和施工附加量所需的费用，应包含在《工程量清单》相应项目有效工程量的每立方米工程单价中，发包人不另行支付。D项，除合同另有约定外，开采土料或砂砾料（包括取土、含水量调整、弃土处理、土料运输和堆放等工作）所需的费用，包含在《工程量清单》相应项目有效工程量的工程单价或总价中，发包人不另行支付。E项，除合同另有约定外，承包人在料场开采结束后完成开采区清理、恢复和绿化等工作所需的费用，包含在《工程量清单》“环境保护和水土保持”相应项目的工程单价或总价中，发包人不另行支付。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]