[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107113":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107113,782,2,"多选题","工程计量的方法包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","现场测量",true,{"key":16,"text":17,"correct":14},"B","按设计图纸计量",{"key":19,"text":20,"correct":21},"C","按工程量清单计量",false,{"key":23,"text":24,"correct":14},"D","按单据计算",{"key":26,"text":27,"correct":14},"E","仪表测量","ABDE","工程计量是发包人向承包人支付工程价款的主要依据，监理人应按合同技术条款中有关计量与支付的规定严格执行。计量方法一般在技术条款、工程量清单前言中规定，实际计量方法必须与合同文件所规定的计量方法相一致，一般情况下有以下几种方法：①现场测量；②按设计图纸计量；③仪表测量；④按单据计算；⑤按监理人批准计量；⑥合同中个别采用包干计价项目的计量。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]