[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107112":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107112,782,2,"多选题","资金使用计划的编制方法包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","按工程投资构成编制资金使用计划",true,{"key":16,"text":17,"correct":18},"B","按工程造价控制目标编制资金使用计划",false,{"key":20,"text":21,"correct":18},"C","按工程项目规模编制资金使用计划",{"key":23,"text":24,"correct":14},"D","按工程项目划分组成编制资金使用计划",{"key":26,"text":27,"correct":14},"E","按工程进度编制资金使用计划","ADE","资金使用计划分解结构，直接决定了今后能否进行过程比对。项目结构分解方法不同，资金使用计划的编制方法也有所不同，常见的有：①按工程投资构成编制资金使用计划；②按工程项目划分组成编制资金使用计划；③按工程进度编制资金使用计划。这三种不同的编制方法可以有效地结合起来，组成一个详细完备的资金使用计划体系。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]