[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107108":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107108,782,2,"多选题","采用工程量清单计价模式的建设项目，其工程量清单（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","与招标文件无关",false,{"key":16,"text":17,"correct":18},"B","由招标人提供",true,{"key":20,"text":21,"correct":18},"C","由招标人填写项目及工程量，投标人填入单价和合价",{"key":23,"text":24,"correct":18},"D","是招标文件的重要组成部分",{"key":26,"text":27,"correct":14},"E","不是施工承包合同的组成部分","BCD","工程量清单是一份由招标人提供的文件，它是招标工程项目名称和相应数量的明细清单。它将招标工程的全部项目，按一定的方式进行分解，采用表格形式详细列出包括具体的施工项目及其计量单位、数量、单价、合价等项内容的一份清单，由招标人填写项目及工程量栏，投标人填入单价和合价栏。投标人未填写的单价和合价，视为此项费用已包含在工程量清单的其他单价和合价中。因此，工程量清单是建设项目招标文件的重要组成部分，也是施工承包合同的重要组成部分。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]