[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107106":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107106,782,2,"多选题","施工合同按计价方式可分为（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","总价合同",true,{"key":16,"text":17,"correct":18},"B","固定价格合同",false,{"key":20,"text":21,"correct":14},"C","单价合同",{"key":23,"text":24,"correct":18},"D","可调价格合同",{"key":26,"text":27,"correct":14},"E","成本加酬金合同","ACE","按合同计价方式，施工合同可分为：①总价合同。指支付给承包人的款项在合同中是一个“规定的金额”，即总价。它是以图纸以及工程量清单和说明书为依据，由承包人与发包人经过商定或承包人依据招标文件进行报价确定；②单价合同。指工程量变化幅度在合同规定范围之内，合同双方按认可的工程单价和实际完成且经质量认证合格的工程量，进行工程价款结算的承包合同；③成本加酬金合同。成本加酬金合同也称成本补偿合同，即发包人向承包人支付实际工程成本中的直接费，按事先协议好的某一种方式支付管理费以及利润的一种合同方式。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]