[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107096":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107096,782,2,"多选题","可行性研究阶段编制投资估算与编制设计概算是相同的有（ ）等。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","组成内容",true,{"key":16,"text":17,"correct":14},"B","项目划分",{"key":19,"text":20,"correct":14},"C","费用构成",{"key":22,"text":23,"correct":24},"D","编制方法",false,{"key":26,"text":27,"correct":24},"E","计算标准","ABC","可行性研究投资估算组成内容、项目划分和费用构成与设计概算基本相同，但两者设计深度不同。设计阶段和设计深度决定了投资估算与设计概算在编制方法和计算标准上有所不同。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]