[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107092":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107092,782,2,"多选题","下列关于概率树分析的说法中，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","经济评价的概率分析主要是主观概率分析",true,{"key":16,"text":17,"correct":18},"B","概率树分析是一种定性分析方法",false,{"key":20,"text":21,"correct":14},"C","通常假定风险变量之间是相互独立",{"key":23,"text":24,"correct":18},"D","财务（经济）净现值大于等于零的累计概率值越大，风险越大",{"key":26,"text":27,"correct":14},"E","期望净现值为各加权净现值之和","ACE","A项，主观概率通常指以人为预测和估计为基础的概率，客观概率通常指以客观统计数据为基础的概率，经济评价的概率分析主要是主观概率分析。B项，概率树分析是常用的风险分析方法之一，它是利用概率来研究和预测不确定性因素对项目经济评价指标影响的一种定量分析方法。C项，概率树分析是假定风险变量之间是相互独立的。D项，财务（经济）净现值大于等于零的累计概率值越大，风险越小。E项，将各种情况可能发生的概率分别与其对应的净现值相乘，得出加权净现值；将各种情况下的加权净现值相加，即为期望净现值。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]