[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107087":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107087,782,2,"多选题","关于现金流量图，下列说法中正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","现金流量图用来表示各现金流入流出与相应时间的对应关系",true,{"key":16,"text":17,"correct":18},"B","项目计算期指的是项目的运行期",false,{"key":20,"text":21,"correct":14},"C","横轴表示一个从0开始到以的时间序列，每个刻度表示一个时间单位",{"key":23,"text":24,"correct":18},"D","建设开始年为计算期的第0年",{"key":26,"text":27,"correct":14},"E","相对于时间坐标的垂直线代表不同时间点的现金流量大小","ACE","现金流量图用来表示各现金流入流出与相应时间的对应关系的数轴图形。横轴表示一个从0开始到以的时间序列，每个刻度表示一个时间单位。相对于时间坐标的垂直线代表不同时间点的现金流量大小。B项，项目计算期是指项目经济评价中为进行动态分析所设定的期限，包括项目的建设期和运行期。D项，建设开始年作为计算期的第一年，年序为1。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]