[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107084":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107084,782,2,"多选题","计算水利工程造价时，应从工程项目总投资中扣除的包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","劳保支出",true,{"key":16,"text":17,"correct":14},"B","施工机械设备购置费",{"key":19,"text":20,"correct":14},"C","生产职工培训费",{"key":22,"text":23,"correct":24},"D","建设期融资利息",false,{"key":26,"text":27,"correct":14},"E","与工程无直接关系的工程投资","ABCE","水利工程造价也称工程净投资，是指在工程项目总投资中扣除回收金额、应核销投资和与本工程无直接关系的转出投资后的余额。新版章节练习，考前压卷，金考典软件考前更新，下载链接 www.jinkaodian.com回收金额，一是指保证工程建设而修建的临时工程，施工后已完成其使命，需进行拆除处理，并回收其余值；二是指项目法人采购的施工机械设备购置费的回收。应核销的投资支出，一般包括：生产职工培训费，施工机构转移费，职工子弟学校经费，劳保支出，不增加工程量的停、缓建维护费，拨付给其他单位的基建投资，移交给其他单位的未完工程，撒废工程的损失等。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]