[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107077":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107077,782,2,"多选题","下列关于建设项目投资控制的说法中，不正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目投资控制的重点在于施工阶段",true,{"key":16,"text":17,"correct":18},"B","项目作出投资决策后，控制项目投资的关键在于设计",false,{"key":20,"text":21,"correct":14},"C","建设项目投资控制工作的目标是使建设项目整个寿命周期投资总额最小",{"key":23,"text":24,"correct":18},"D","建设项目的投资、工期与质量三者是辩证统一的关系，它们是相互依存和影响的",{"key":26,"text":27,"correct":14},"E","建设项目投资控制只考虑工程建设投资","ACE","A项，项目投资控制的重点在于施工以前的投资决策和设计阶段，而在项目作出投资决策后，控制项目投资的关键就在于设计；C项，建设项目投资控制工作的目标应是在满足功能要求的前提下，使建设项目整个寿命周期投资总额最小；E项，建设项目投资控制考虑的是项目整个寿命周期的费用，包括工程建设投资、营运费用和报废拆除费用。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]