[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107061":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107061,782,2,"多选题","可行性研究的具体任务包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","项目建设的必要性研究",true,{"key":16,"text":17,"correct":14},"B","技术路线可行性研究",{"key":19,"text":20,"correct":21},"C","利润最大化研究",false,{"key":23,"text":24,"correct":14},"D","项目实施计划研究",{"key":26,"text":27,"correct":21},"E","社会价值研究","ABD","可行性研究的具体任务包括项目建设的必要性研究、技术路线可行性研究、工程条件的研究、项目实施计划研究、资金使用计划和成本核算的研究，人员培训计划研究和效益评价研究等内容。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]