[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107004":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1107004,782,2,"多选题","计量双侧控制图包括的内容有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","平均值-极差双侧控制图",true,{"key":16,"text":17,"correct":18},"B","缺陷数双侧控制图",false,{"key":20,"text":21,"correct":18},"C","单位缺陷数双侧控制图",{"key":23,"text":24,"correct":14},"D","中位数-极差双侧控制图",{"key":26,"text":27,"correct":14},"E","单值-移动极差双侧控制","ADE","本题考查的是常用的质量分析方法。B、C错误，属于计数双侧控制图内容。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]