[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106970":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106970,782,2,"多选题","关于碾压施工质量及压实度的检验，以下说法正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","碾压机械行走方向应垂直子填筑面轴线",false,{"key":16,"text":17,"correct":14},"B","分段、分片碾压，相邻作业面的搭接碾压宽度，平行填筑面轴线方向不应小于1m",{"key":19,"text":20,"correct":21},"C","拖拉机带碾磙或振动碾压实作业，宜采用进退错距法",true,{"key":23,"text":24,"correct":21},"D","机械碾压时应控制行车速度，以不超过下列规定为宜，平碾为2km\u002Fh",{"key":26,"text":27,"correct":21},"E","机械碾压不到的部位，应辅以夯具夯实","CDE","碾压施工质量及压实度的检验：①碾压机械行走方向应平行子填筑面轴线。②分段、分片碾压，相邻作业面的搭接碾压宽度，平行填筑面轴线方向不应小于0.5m，垂直填筑面轴线方向不应小于1.5m。③拖拉机带碾磙或振动碾压实作业，宜采用进退错距法，碾迹搭压宽度应大于10cm。铲运机兼作压实机械时，宜采用轮迹排压法，轮迹应搭压轮宽的1\u002F3。④机械碾压时应控制行车速度，以不超过下列规定为宜，平碾为2km\u002Fh，振动碾为2km\u002Fh，铲运机为2挡。⑤机械碾压不到的部位，应辅以夯具夯实。夯实时应采用连环套打法，夯迹双向套压，夯压夯1\u002F3，行压行1\u002F3；分段、分片夯实时，夯迹搭压宽度应不小于1\u002F3夯径。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]