[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106962":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106962,782,2,"多选题","工程验收的意义包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","检查已完工程在设计.施工.设备制造安装等方面的质量",true,{"key":16,"text":17,"correct":18},"B","检查工程投资控制和资金落实情况",false,{"key":20,"text":21,"correct":14},"C","检查工程是否具备运行或进行下一阶段建设的条件",{"key":23,"text":24,"correct":14},"D","总結工程建设中的经验教训，并对工程做出评价",{"key":26,"text":27,"correct":14},"E","及时移交工程，尽早发挥投资效益","ACDE","本题考查的是工程验收。B错误，工程验收的意义是检查工程投资控制和资金使用情况而不是落实情况。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]