[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106956":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106956,782,2,"多选题","关于竣工验收的规定，说法错误的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","竣工验收应当在工程建设项目全部完成并满足一定运行条件后3年内进行",true,{"key":16,"text":17,"correct":14},"B","不能按期进行竣工验收的，经竣工验收主持单位同意，可以适当延长期限，但最长不得超过3个月",{"key":19,"text":20,"correct":21},"C","竣工财务决算应当由竣工验收主持单位组织审查和审计",false,{"key":23,"text":24,"correct":21},"D","竣工财务决算审计通过15日后，方可进行竣工验收",{"key":26,"text":27,"correct":21},"E","竣工验收主持单位应当自收到竣工验收申请之日起20个工作日内决定是否同意进行竣工验收","AB","竣工验收应当在工程建设项目全部完成并满足一定运行条件后1年内进行。不能按期进行竣工验收的，经竣工验收主持单位同意，可以适当延长期限，但最长不得超过6个月。逾期仍不能进行竣工验收的，项目法人应当向竣工验收主持单位作出专题报告。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]