[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106955":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106955,782,2,"多选题","以下单位工程施工质量可评为合格的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","工程施工期及试运行期，单位工程观测资料分析结果符合国家和行业技术标准以及合同约定的标准要求",true,{"key":16,"text":17,"correct":14},"B","所含分部工程质量全部合格",{"key":19,"text":20,"correct":14},"C","质量事故已按要求进行处理",{"key":22,"text":23,"correct":24},"D","工程外观质量得分率达到50%以上",false,{"key":26,"text":27,"correct":14},"E","单位工程施工质量检验与评定资料基本齐全","ABCE","单位工程施工质量同时满足下列标准时，其质量评为合格：①所含分部工程质量全部合格；②质量事故已按要求进行处理；③工程外观质量得分率达到70%以上；④单位工程施工质量检验与评定资料基本齐全；⑤工程施工期及试运行期，单位工程观测资料分析结果符合国家和行业技术标准以及合同约定的标准要求。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]