[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106942":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106942,782,2,"多选题","工程设备安装完毕后，要参与和组织的调试有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","单体调试",true,{"key":16,"text":17,"correct":18},"B","双体调试",false,{"key":20,"text":21,"correct":14},"C","联体无负荷调试",{"key":23,"text":24,"correct":14},"D","联体有负荷调试",{"key":26,"text":27,"correct":18},"E","全系统调试","ACD","本题考查的是施工实施阶段影响因素的质量控制。工程设备安装完毕后，要参与和组织单体、联体无负荷和有负荷的调试。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]