[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106934":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106934,782,2,"多选题","在工程项整个建设周期内，属于施工方法质量控制内容的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","技术方案",true,{"key":16,"text":17,"correct":18},"B","专家论证",false,{"key":20,"text":21,"correct":18},"C","合同措施",{"key":23,"text":24,"correct":14},"D","检测手段",{"key":26,"text":27,"correct":14},"E","施工组织设计","ADE","本题考查的是施工实施阶段影响因素的质量控制。施工方法的质量控制，包含工程项自整个建设周期内所采取的技术方案、工艺流程、组织措施、检测手段、施工组织设计等的控制。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]