[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106932":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106932,782,2,"多选题","为完成合同约定的各项工作，承包人应向施工场地派遣或雇佣足够数量的人员，其中包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","具有相应规模的农民工",false,{"key":16,"text":17,"correct":18},"B","具有相应资格的专业技工和合格的普工",true,{"key":20,"text":21,"correct":18},"C","具有相应施工经验的技术人员",{"key":23,"text":24,"correct":14},"D","具有相应资质的检验检测人员",{"key":26,"text":27,"correct":18},"E","具有相应岗位资格的各级管理人员","BCE","本题考查的是施工准备阶段影响因素的质量控制。为完成合同约定的各项工作，承包人应向施工场地派遣或雇佣足够数量的下列人员：具有相应资格的专业技工和合格的普工；具有相应施工经验的技术人员；具有相应岗位资格的各级管理人员。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]