[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106920":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1106920,782,2,"多选题","对于调试工作质量控制可分为（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","质量检查阶段",true,{"key":16,"text":17,"correct":18},"B","生产性介质投料的联合试运转阶段",false,{"key":20,"text":21,"correct":14},"C","单体调试阶段",{"key":23,"text":24,"correct":14},"D","有负荷调试",{"key":26,"text":27,"correct":14},"E","无负荷或非生产性介质投料的联合调试","ACDE","工程设备安装完毕后，要参与和组织单体、联体无负荷和有负荷的调试。对于调试工作质量控制可分为以下四个阶段：①质量检查阶段。②单体调试阶段。③无负荷或非生产性介质投料的联合调试。④有负荷调试。",{"id":6,"name":31,"category":32,"favorite":33},"目标控制（水利工程）","建筑工程",0]