[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106901":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106901,782,1,"单选题","下列属于BIM在施工进度管理中的优点的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直观高效地表达多维空间数据",true,{"key":16,"text":17,"correct":18},"B","支持施工主体实现“先建后试”",false,{"key":20,"text":21,"correct":18},"C","工程施工进度跟踪十分困难",{"key":23,"text":24,"correct":18},"D","在处理施工进度偏差时缺乏整体性","传统进度管理存在的主要问题包括：①项目信息丢失现象严重；②无法有效发现施工进度计划中的潜在冲突；③工程施工进度跟踪十分困难；④在处理施工进度偏差时缺乏整体性。BIM在施工进度管理中的价值在于：①BIM能直观高效地表达多维空间数据，避免了用二维图纸作为信息传递媒介带来的信息损失，从而使项目参与人员在最短时间内领会复杂的勘察设计信息，减少沟通障碍和信息丢失；②支持施工主体实现“先试后建”；③为工程参建主体提供有效的进度信息共享与协作环境；④支持施工进度管理与资源管理的有机集成。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]