[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106897":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1106897,782,1,"单选题","定义项目日期中，必须完成（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","在用关键路线算法进行进度计算时，影响采用自由浮时参数确定的关键路线",false,{"key":16,"text":17,"correct":14},"B","只在无任何作业项时，才能够显示",{"key":19,"text":20,"correct":14},"C","系统给出，不能手动定义",{"key":22,"text":23,"correct":24},"D","在用关键路线算法进行进度计算时，影响后推法计算最晚时间",true,"本题考查的是OraclePrimaveraP6软件。定义项目日期中，必须完成：在用关键路线算法进行进度计算时，影响后推法计算最晚时间，影响自由浮时和总浮时参数，影响采用总浮时参数确定的关键路线。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]