[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106895":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1106895,782,1,"单选题","不属于传统进度管理存在的主要问题的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目信息丢失现象严重",false,{"key":16,"text":17,"correct":14},"B","无法有效发现施工进度计划中的潜在冲突",{"key":19,"text":20,"correct":14},"C","工程施工进度跟踪十分困难",{"key":22,"text":23,"correct":24},"D","在处理质量偏差时缺乏整体性",true,"本题考查的是BIM技术应用。传统进度管理存在的主要问题包括：①项目信息丢失现象严重；②无法有效发现施工进度计划中的潜在冲突；③工程施工进度跟踪十分困难；④在处理施工进度偏差时缺乏整体性。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]