[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106893":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106893,782,1,"单选题","在“前置任务”中填写与之相关的任务编号时，MS Project 会自动连接（ ）任务。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","一个",false,{"key":16,"text":17,"correct":18},"B","两个",true,{"key":20,"text":21,"correct":14},"C","多个",{"key":23,"text":24,"correct":14},"D","三个","本题考查的是Microsoft Project软件。在“前置任务”中填写与之相关的任务编号 （非大纲数字\u002FWBS编号）时，MS Project 会自动连接两个任务。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]